Contract Name: Commercial Pedestrian Bridge Repairs
Value: £4.5k
Date of Project: December 2020
Customer: AM Defence and Marine Ltd
This scaffold was designed to allow for the handrails and surface of the bridge to be repaired whilst maintaining pedestrian access and ensuring a safe passage to the public.
Contract Name: Broadwalk House Exeter
Value: £10.5k
Date of Project: December 2020
Customer: Gilpin Demolition
This job include the demolition of internal office spaces that were being converted into student accommodation over 3 floors.
Pictures show external elevation and contained fully lit pedestrian footway
Contract Name: Tremough Campus Falmouth
Value: £1700
Date of Project: December 2020
Customer: Bouygues
This job was awkward as it had to go up in the middle of a live library. So, the noise had to be kept to a minimum and we worked around the students coming in and out of the buildings.
Contract Name: Launceston Barns
Value: > £10k
Date of Project: October 2020
Customer: Pollard Construction
The old barns already had scaffolding, however, it was poor quality, so we dismantled them and erected our own scaffolding.
Contract Name: St Cleer Farmhouse
Value: £10k
Date of Project: October 2020
Customer: Gilpin Envrionmental
We constructed a scaffold birdcage with over 600 scaffold boards inside an old chicken farmhouse in St Cleer.
Contract Name: St Nuns Church, Grampound
Value: £4k
Date of Project: September – December 2020
Customer: Rothwell Historical Restoration
Contract Name: Mayflower Water Treatment Works
Value: £7.2k
Date of Project: 10/07/2020
Customer: Sungift Solar
Contract Name: School in Doubletrees, Cornwall
Value: £12.5k
Date of Project: July 2020
Customer: Special school in Doubletrees
We recently completed a job on a special needs school in Doubletrees. This had to be done whilst working closely with the tenants who had children in care at the time and had special time frames which we had to work around.
Contract Name: Street scaffolding in Looe
Value: £10k
Date of Project: early 2020
Customer: Black Swan Public House
The works here involved a street permit along with designs for going over the joining shop roofs.
Contract Name: Swimming pool/Leisure centre in Tavistock, Devon
Value: £34k
Date of Project: December 2019
Customer: Devon Contractors
We completed this job in Tavistock for Devon Contractors – this had to be done at night time over the swimming pool which was still being used during the day. This was spanned over the pool area and water slide to install new trusses within the extension
Contract Name: Charlestown Chapel
Value: £9.6k
Date of Project: October 2019
Customer: Broad Developers
This was completed on a restoration to an old church in Charlestown for Broad Developers. This had difficulties on the works as it is a listed building and also overhead wires
Contract Name: Physics Building, Exeter University.
Value: £100k
Date of Project: Summer 2018
Customer: Morgan Sindall
Design scaffold to external perimeter of the physics building, Exeter to take 4 no mast climber units to all elevations. Scaffold also had to bridge over a busy access road with a basement beneath where scaffold could only bear down onto existing party walls. We also had to be very aware of all shrubbery and trees within the vicinity as many rare and endangered species were in place around the area to be scaffolded.
Contract Name: Heathcoat Fabrics, Tiverton
Value: £75k
Date of Project: Spring 2018
Customer: Devon Contractors
Another difficult design scaffold to form a birdcage type scaffold constructed up of an existing dog tooth roof with over 1500 boards on it to give access to the new roof structure being erected above whilst acting as a safety crash deck to the live factory below. Within our design we also had to incorporate a protective temporary roof system over a large piece of equipment that had to be kept dry at all times.
Contract Name: Torquay Academy
Value: £35k
Date of Project: Spring 2018
Customer: Morgan Sindall
Fully boarded scaffold to external envelope of a busy live school . Erected initially for steel frame erection then subsequently adapted for various external finishes including steel panels, glass, and brickwork.
Contract Name: Millwood House
Value: £6700
Date of Project: 2015
Customer: Low Carbon Exchange
This contract was for edge protection and a staircase access for installing the Solar Panels to the main roof. The building and car park were live during the installation, so extra precautions were used to protect the public as we erected and dismantled the scaffolding. The job was completed on time and the client was delighted.
Contract Name: Ilfracombe Academy
Value: N/A
Date of Project: 2016
Customer: BAM
This high profile project required a high level guard rails to provide safe roof edge protection. The guardrails running for approximately 180m were designed as per TG20:13 Access to the roof was provided using Universal staircases contained within traditional tube & fitting towers.